केन-बेतवा लिंक परियोजना प्राधिकरण

Ken-Betwa Link Project Authority

Ministry Logo

Progress as on 31-05-2026

Components under Execution by KBLPA

Ken-Betwa Link Project Authority

EPC Contractor: M/s NCC Ltd.
  • Contractor Mobilization and Site Establishment: Contractor has mobilized adequate man power and construction equipment. Infrastructure works are in advance stage of completion. Machinery, batching plants, and crusher plants are being installed/erected. .
  • 33 KV Transmission Line: Stage-II forest clearance obtained on 30.01.2026. Physical progress is about 52%.
  • Approach Roads: Subgrade and culvert works on Roads 1 ( Daudhan Dam to Bhusor Gate – 6.715 km) and Road 2 (Bhusor Gate to NH 39 at Bamitha – 13.883 km) largely completed. Construction of Road 3 (4.5 km) and Road 4 (18.34 km) could not be started due to land acquisition issues which are being pursued.. Physical progress is about 24%.
  • Office and Residential Complex:work in different buildings is at different stages. Generally, Foundations and plinth-level works have been completed; superstructure works in progress. Overall progress is about 17%.
  • Coffer Dam:Closing of the periphery of coffer dam has been completed. Raising of the embankment level and it strengthening is under progress (Progress is about 76.59%)
  • Concrete Dam and Spillway: Foundation excavation of Dam blocks 1 to 9 completed and is under progress with progress of 4.25% in dam blocks from 10 to 48. About 3.00 lakh cum quantity of foundation excavation is completed. Concreting in Dam block 1 to 5 has commenced from 21 May 2026.
  • Approach Channel and Upper Level Tunnel:Excavation of approach channel for upper level tunnel and lower level tunnel is under progress and about 20% excavation of approach channel completed. Construction of outlet portal of upper level tunnel has started with wiremesh installation and shotcrete works currently in progress. Achived tunnel crown level-EL-262 mts till now this month 2880 cum excavation & installation of SDA, wiremesh and shotcrete is under progress.

II. Ken–Betwa Link Canal

Tender Document Preparation: The Steering Committee of Ken-Betwa Link Project (SC-KBLP), in its 8th meeting approved EPC tendering for the Ken-Betwa Link Canal in two packages i.e. Package-1 from Upper-Level Tunnel outlet (Beyond scope of EPC contract of Daudhan Dam) to near River Dhasan and Package-II from the River Dhasan to outfall at Barwa Sagar dam. The tender documents for both packages after approval of Technical Advisory Group (TAG) and Tender Evaluation Committee (TEC) has been submitted to the Ministry for approval on 22-04-2026. The Government of India issued the Mother Sanction for Land Acquisition (LA) and Rehabilitation & Resettlement (R&R) on 15.06.2026. In continuation of the same, Administrative Approval was also accorded on 15.06.2026. All necessary actions related to Land Acquisition are currently under process at the administrative level.

Components under Execution by Government of Uttar Pradesh

Irrigation & Water Resources Department, UP

Restoration of Ken Canal system

Project is under construction and total physical progress is about 40%.

Repair & Renovation of Tanks

DPR prepared and uploaded to CWC's e-PMS portal for approval.

Modernization of Weirs and Dams

Repair of Bariyarpur PUW, Parichha Weir, Barwa Sagar Dam and other appurtenant Structures- DPR submitted to CWC for appraisal by I&WRD, UP in July 2025

Pailani Barrage

DPR is in appraisal by CWC.

Banda Barrage

DPR is under preparation by NWDA and is expected to be completed by June 2026

Pumping & Pressurized Irrigation

Developing pumping system, pipe distribution network and micro irrigation System from Ken Betwa link canal to serve 17,488 ha of enroute commands and ii) Development of new command area 37,564 ha in Mahoba district of Uttar Pradesh with pressurized pipe micro irrigation system - The cost appraisal has been approved by CWC on 26.11.2025. Next stage of approval will be taken in concurrence of the progress of the execution work of Ken - Betwa Link Canal.

Components under Execution by Government of Madhya Pradesh

Water Resources Department, MP

DPR is approved by CWC on 30-01-2026. Tender Document is under preparation

The DPR has been prepared and technically vetted by WRD, BODHI and submitted to CWC by e-PAMS portal on 21.04.2026.

The DPR has been technically vetted by WRD, BODHI and submitted to CWC by e-PAMS portal for approval

PDPR is under preparation by NWDA

Headworks

100%

Canal

49%

Total work Completed

73%

Headworks
86%
Canal
76%
Total
81%

Madia Dam
100%
Chakarpur Dam
100%
Canal
68%
Dehra Power House
0%
Semraghat Weir
0%
Approved Project Cost

₹44,605 Cr

All Components Combined

Central Share

₹36,289 Cr

81.4% of Total Cost

MP State Share

₹6,171 Cr

13.8% of Total Cost

UP State Share

₹2,145 Cr

4.8% of Total Cost

Total Component Wise Allocation

Total: Rs. 44,605 Cr.

Component-Wise Details

Component Details
Component I (90:10) Dhaudhan Dam (Civil Works), Dhaudhan Dam (Land Acquisition and R & R), Pumping Arrangement, K B Link Canal (Main), Ken Left Bank Canal (LBC) System, Bye-pass Channel from Exit of LLT to connect to Ken Left Bank Canal (LBC) of MP for 2.2 KMs, Panna and Hatta Lift Canal System, Micro Irrigation & Command Area Development in UP, RRR of Ken Canal System of UP, Renovation of Mahoba Tank with its Connecting Canal, Repairing & Strengthening of Bariyapur PUW, Parichha Weir, Barwa Sagar etc.
Component II (60:40) Lower Orr Project, Kotha Barrage Project, Bina Complex Project, Two New Barrages of UP (Proposed Banda & Pailani Barrages) (subject to DPR Preparation)
Component III (MP Funded) Power House I & II and Power Component of Lower Orr Project, Kotha Barrage Project, Bina Complex Project

Component wise Stack-Holder Funding Contribution

Component I
Total: Rs. 33,593.76 Cr.
Component II
Total: Rs. 10,091.23 Cr.
Component III
Total: Rs. 919.99 Cr.

Component and Implementing wise Expenditure as on 31-05-2026